2 adjacent gully drains completely blocked with building debris

Reported in the Gully/Drainage category anonymously at 12:56, Tuesday 17 September 2019

Sent to Bristol City Council 4 minutes later

2 adjacent gully drains outside 26 Ambra Vale are completely blocked from building debris (mud, stones) which appears to have originated from further up Ambra Vale. Remains of a flow of debris can still be clearly seen in the gutter leading into the gully drains. This has occurred sometime between 6 September and 15 September 2019. As these gullies are on a steep hill, this substantial blockage will result in much increased water flow down Ambra Vale (especially during a downpour / thunderstorm), and could lead to water ingress into a neighbouring house.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Under investigation.

    Posted by Bristol City Council at 13:00, Tuesday 17 September 2019

  • Under investigation.

    Posted by Bristol City Council at 13:57, Tuesday 17 September 2019

  • Job raised.

    Posted by Bristol City Council at 14:20, Monday 23 September 2019

  • Job raised.

    Posted by Bristol City Council at 14:20, Monday 23 September 2019

  • NB Wessex Water who are currently working at 30 Ambra Vale were NOT working at this site when the gullies became blocked.

    Posted anonymously at 17:27, Monday 23 September 2019

  • Customer follow up.

    Posted by Bristol City Council at 17:30, Monday 23 September 2019

  • Job raised.

    Posted by Bristol City Council at 12:56, Wednesday 25 September 2019